The progress of the construction of a residential house in Truskavets

According to our project, construction of a four-section apartment house in Truskavets, Lviv region.

trusk_000

The first section has 4 floors. The technical floor is completed and the roof is being constructed. On the second and third sections the foundations are laid, the first floor is being built.

trusk_001

trusk_002

trusk_003

We closely monitor the implementation process of our projects. We will inform about the course of work on the site and from now on.